Deck Footing Calculator
Footing count, concrete volume and bag counts per footing — the deck-side companion to our concrete tools.
Please check your inputs — values must be within the allowed ranges.
How many footings does my deck need?
The honest answer: it's set by your beam size, joist span and local code — not by a formula. But the common residential starting point is footings spaced 6 to 8 ft apart along each beam, with one at each end. That's what the calculator uses as a reference layout:
- Attached deck (ledger board on the house): one beam line carries the far edge — footings = beam length ÷ spacing, rounded up, + 1.
- Freestanding deck: two beam lines — double the count.
For the code-side sizing tables (beam span vs. footing size), see the IRC deck provisions or your local building department. Treat this calculator's count as a planning estimate, not a stamped design.
Concrete volume per footing
Each round footing is a cylinder:
Volume = π × (diameter ÷ 24)² × depth (ft) — diameter in inches, because (d ÷ 2 ÷ 12) is the radius in feet.
A 12-in diameter footing — the default for typical 6x6 deck posts — at common depths, with 10% waste:
| Depth | Volume | 80 lb bags per footing |
|---|---|---|
| 24 in (2 ft) | 1.57 cu ft | 3 |
| 36 in (3 ft) | 2.36 cu ft | 5 |
| 42 in (3.5 ft) | 2.75 cu ft | 6 |
| 48 in (4 ft) | 3.14 cu ft | 6 |
Bell-shaped or flared footing bases add volume — the cylinder math here is the straight-shaft minimum.
How deep should deck footings be?
Below your local frost line (frost depth) — the depth to which ground freezes in winter. Footings that sit above it get heaved and tilted by freeze-thaw cycles, which is what makes decks lean over the years.
- Mild climates (coastal south, west coast): often 12–18 in
- Temperate mid-continent: 30–36 in
- Cold northern states: 42 in or more — the 3.5-ft default here is a typical northern requirement
Your city or county building department publishes the required frost depth — check it before ordering concrete, because depth is the single biggest driver of your bag count.
Bags vs. ready-mix
| Total concrete | Better option | Why |
|---|---|---|
| Under ~1 cu yd (up to ~10 footings @ 12×42 in) | Bags (80 lb) | No delivery minimum, mix as you go, pour one hole at a time |
| Over ~1–1.5 cu yd | Ready-mix truck | Cheaper per yard, one continuous pour, no mixing labor — but often has a delivery minimum |
For exact bag math on any pour size, use the concrete calculator or the bag-focused concrete bags calculator.
Sources & assumptions
- Footing spacing reference (6–8 ft along beam): common residential practice consistent with the IRC deck provisions (Table R507 series) — reference only, not a design ruling.
- Cylinder volume π × r² × h: plain geometry.
- Bag yield (80 lb ≈ 0.6 cu ft): published yield data for QUIKrete Concrete Mix.
- Frost depth guidance (12–42+ in by climate): typical U.S. requirements — your local building department's number is the one that counts.